The government had paid out almost RM273 million for a new customs system that was never delivered.
However, in the end, the project failed to be completed, with only 27.2 percent of deliverables delivered.
According to the Auditor-General's 2019 report Series 2 - the uCustoms system project was initiated in 2013 and was supposed to complete in 2015.